Network Work at the Campuses
As part of the upgrade of our university-wide network, we will be making adjustments to the network infrastructure at the campuses in the coming weeks.
The work will take place after the exam period ends and during the break between semesters.
ATTENTION Please note that there will be no internet connection in the affected building sections during the relevant time periods.
2026 Schedule
Start: July 6, 2026
Estimated end: July 17, 2026
Wilhelmshaven
- Main Building
- East Building
- Administration Wing
Schedule:
- Main Building, 1st floor – Mon., July 6, 2026
- Main Building, 2nd floor – Tue., July 7, 2026
- Main Building, 3rd floor – Wed., July 8, 2026
- East Building, Section O10 – Thu., July 9, 2026
- East Building, Section 025 – Fri., July 10, 2026
- Administration Wing – Mon, July 13, 2026
As part of this construction project, individual buildings on the Oldenburg campus (Geo, Lib, HL) may also be migrated in 2026. Information regarding this will be provided well in advance.
2027 Schedule
Oldenburg
Details will follow in due course.
If, after the migration, a wired device is unable to establish a network connection, please submit a ticket to the Service Desk at https://servicedesk.jade-hs.de with the subject line “Network WHV + Room.” If you are unable to submit a ticket, we are also available to assist you in person at the HRZ.